| Project |
|
| Client |
| | U.S. Army Corps of Engineers |
|
| Role |
| | Prime contractor for deepening of the Kill Van Kull Channel |
|
| Contract |
| | Value: $115,000,000
Duration: 950 Days
Years: 2008-2011 |
|
| Description |
| | The project entails mechanical dredging of 2.3 million cubic yards of mud, sand, glacial till and solid rock within New York Harbor and Kill Van Kull Channel with disposal at five sites, including four artificial reefs within the Atlantic Ocean. |
|
| |